Reducing Project Duration
The president of a software company remarks in a speech that new technologically advanced software will be available in one year. This is an example of reducing project duration caused by:
A)
Imposed project deadlines
B)
Time to market
C)
Unforeseen project delays
D)
High overhead
E)
Incentive contracts
Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an example of reducing project duration caused by:
A)
Imposed project deadlines
B)
Time to market
C)
Unforeseen project delays
D)
High overhead
E)
Incentive contracts
Which of the following is not considered a project indirect cost?
A)
Supervision
B)
Consultants
C)
Equipment
D)
Interest
E)
All of these are considered project indirect costs
Low-cost, realistic, efficient methods for completing an activity under normal conditions are supported by ____ time.
A)
Normal
B)
Budget
C)
Optimized
D)
Expected
E)
Target
5
The shortest possible time an activity can be completed realistically is called ___ time.
A)
Expedited
B)
Accelerated
C)
Crash
D)
Optimistic
E)
Optimal
6
____ costs are incurred when completing an activity in its realistically shortest time.
A)
Normal
B)
Reserve
C)
Crash
D)
Accelerated
E)
Expedited
Cost slope can be determined by dividing the
A)
Run by the rise
B)
Rise by the run
C)
Crash cost by the normal cost
D)
Normal cost by the crash cost
E)
Both B and C are
Which of the following ly calculates an activity’s cost slope?
A)
(normal cost-crash cost)/(normal time-crash time)
B)
(crash cost-normal cost)/(normal time-crash time)
C)
(normal time-crash time)/(crash cost-normal cost)
D)
(normal time-crash time)/(normal cost-crash cost)
E)
(crash cost-normal cost)/(crash time-normal time)
The optimum duration for a project is at the point where:
A)
Direct costs are the lowest
B)
Indirect costs are the lowest
C)
Direct costs equal indirect costs
D)
Total project costs are the lowest
E)
The project changes from time-constrained to resource-constrained
Creating a Project Cost-Duration graph is useful:
A)
During the pre-project planning phase
B)
After the project has begun
C)
After the completion of the project
D)
Both A and B are
E)
A, B, and C are all
If a network has several critical or near-critical paths it is deemed to be:
A)
Well planned
B)
The lowest cost alternative
C)
Resource-constrained
D)
Sensitive
E)
Insensitive
A positive situation where moving toward the optimum time can result in very real, large savings—this occurs when the network is:
A)
Insensitive
B)
Sensitive
C)
Ahead of schedule
D)
Shifting to the critical chain
E)
Implementing a fast-tracking system
13
Which of the following is the most common method for shortening project time?
A)
Assigning additional staff and equipment
B)
Subcontract work
C)
Schedule overtime
D)
Reduce project scope
E)
Reduce the quality
14
Which of the following is the easiest method for shortening project time?
A)
Assigning additional staff and equipment
B)
Subcontract work
C)
Schedule overtime
D)
Reduce project scope
E)
Reduce the quality
15
The Snapshot from Practice “Cell-Phone Wars” is an excellent example of reducing project duration due to:
A)
Imposed project deadlines
B)
Time to market
C)
Unforeseen project delays
D)
High overhead
E)
Incentive contracts
Choose an academic level, add pages, and the paper type you want.
To reduce the cost of our essay writing services, select the lengthier deadline.
We can't believe we just said that to you.
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more
Recent Comments